| 01_user_documentation:07_rgg_xl:02_xl:05_rule:02_spo [2025/09/04 12:37] – ↷ Page name changed from 01_user_documentation:07_rgg_xl:02_xl:05_rule:03_spo to 01_user_documentation:07_rgg_xl:02_xl:05_rule:02_spo gaetan | 01_user_documentation:07_rgg_xl:02_xl:05_rule:02_spo [2025/09/04 12:55] (current) – gaetan | ||
|---|---|---|---|
| Line 1: | Line 1: | ||
| ====== SPO ====== | ====== SPO ====== | ||
| + | <code java> | ||
| ==>> | ==>> | ||
| + | </ | ||
| + | |||
| + | The Single Push Out (SPO) Graph replacement rule replace one sub-graph by another graph. The connections between the host graph and the newly-inserted graph need to be specified by the programmer. That means that if, e.g., in a one-dimensional graph '' | ||